Connecting UPS and mains cables from Inspector side
|
Apply LOTO in this part of installation to avoid electrical shock hazard. |
|
Apply Zero energy verification before start connection to power distribution box (PDB). |
At Inspector side, you will have to check that all of short connections are fixed on their proper places. You have two connection options: “Line to Neutral” or “Line to Line”.
You can find the connection guide under the cover of Inspector as shown.
|
Line to Neutral connection is used in SINGLE/THREE PHASE CONNECTION, BUT Line to Line is ONLY used in THREE PHASE CONNECTION. |